Work on hangar continues after bad weather delays

The new hangar at the Burnet Municipal Airport is now 90% complete. After delays from wind and rain, work is back on track.

The new hangar at the Burnet Municipal Airport is now 90% complete.

After delays from wind and rain, work is back on track. The hangar door and metal panels should be finished in two to three weeks, followed by final adjustments.

Electrical work is 50% complete and should wrap up in the next two weeks. Permanent power is expected to be completed mid- May.